SCOPE OF WORK INCLUDED:
LPG Filling Station.
EPCC Engineering, Procurement, Construction & Commissioning of LPG Filling Station.
SPEC being original equipment manufacturer also supplied following equipment from its fabrication facilities located in USA, UAE and Pakistan:
EQUIPMENT INCLUDED:
Engineering
Includes:
- Fire Water System Design
- F&G Detection system
- Civil Design & Engineering of the Station
- Detailed check of existing bullets & recommendations for
- modification required for smooth operation
Vessel Works
Includes:
- Vessel inspection
- R Stamp on all LPG Bullets
- Hydrotest of all bullets
- Painting of vessels (single coat)
- Any repair works
- Structural works on vessels (ladders + platform)
Packages
Includes:
- Manual Filling station
- LPG Loading Pumping Skid
- LPG Filling Pumping Skid
- Compressed Air Package
FireWater Sysem
Includes:
- Engine for FW Pump
- Diesel Driven Pump
- Jockey Pumps
- Diesel Fuel Tank on skid
- Control System
- Fire Hydrants
- Fire Monitors
- Fire Extinguishers
- Sprinkling System
Instrumentation & Control
Includes:
- Instrumentation, LT & PI, TI
- ESDV valves
- SCADA system
- 6 Fire detectors
- HC Detectors
- Flowmeters, micromotion
- Programming of PLC
Generator
Includes:
- Generator with Panel
- Diesel Tank & Diesel Pump
- canopy & ATS Panel
Civil
Includes:
- Office Block
- Resident Block
- Electrical & Generator room
- Tank Supports
- Underground Water tank
- Weigh Bridge & Control Room
- Cylinder Filling station
- Tuff Pavers
- Roads
- Guard Room
- Mosque
- Fire wall
- Backfilling @ Site
- Plumbing of all area
- Storm Water Drainage System
- Sewerage System
- Watch Towers
|